A schedule that loads every work center to capacity builds work in progress in front of the bottleneck. The constraint sets the pace of the whole plant, so it should set the schedule.
Three rules
- Schedule the constraint first, in detail.
- Protect it with a time buffer sized from real run data.
- Release work upstream only at the pace the constraint consumes it.