A useful baseline starts at the machine. Record planned production time, stops, actual cycles and good parts before deciding where to invest.
Count what the machine does, not what the report says
Before a capital request, walk the constraint with each shift and agree how stops are counted. A short stop logged as “running” on one shift and as downtime on another makes every later number argue with itself.
| Factor | Measure | Baseline |
|---|---|---|
| Availability | Run time / planned time | 82.0% |
| Performance | Ideal / actual cycle | 91.0% |
| Quality | Good / total parts | 98.0% |
OEE = Availability × Performance × Quality. With the factors above, the line runs at about 73% OEE before anything is bought.
Sign it before you change it
Have the plant manager sign the baseline before the first improvement. Every later claim, in throughput or in cash, is measured against that signature.