Skip to content

Case study, Precision machining

Precision Hydraulics Machining — Cell Rebalance

Rebalancing machining cells for a hydraulics manufacturer where long setups and scrap held back a growing order book.

Setup time cut (SMED)
34.0%
Scrap reduction
14.2%

Challenge

Machining cells were loaded unevenly and long setups pushed operators to run oversized batches. Scrap rose at the end of long runs and the order book was outgrowing the cells.

Approach

We filmed changeovers with the crews, moved preparation off the critical path and rebalanced work across cells around the constraint machine. Shift handovers were held at the cell, at 5:30 a.m., with the press leads.

Outcome

Setup time fell 34.0% and scrap fell 14.2%, without new capital equipment.

Having Martin and David on the floor at 5:30 a.m. shift handover earned immediate credibility with our press leads.

Plant Director, Precision Hydraulics Group